|
Wednesday,
May 31st,
2006:
-
The interior door installation begins.
-
The final driveway work begins.
-
The interior oak trim installation begins.
Friday,
May 24th,
2006:
-
The septic system and drain field installation begins.
Friday,
May 19th,
2006:
-
The interior trim staining begins.
-
The tiling of the bathrooms are complete, but we're not entirely
happy with some tile along the master bath shower door, so that
will have to be redone.
Thursday,
April 27th,
2006:
-
The front porch columns are installed.
Wednesday,
April 26th,
2006:
-
The
-
The side yard is bush-hogged in preparation for the drain field
installation.
-
The septic tank arrives.
Monday,
April 24th,
2006:
-
Most all of the porch flooring in installed, The
herringbone corner looks great!
-
The drywall is taped and mudded (first coat).
Saturday,
April 22nd,
2006:
-
Pre-primed porch flooring arrives and is hand-sorted.
Selected pieces are brought back to our shop for special
milling. This operation is needed since we're going to use
a rather decorative "herringbone weave" for the curved section
of the porch where the porch boards change direction. This
technique requires that these "tongue & groove" boards have
additional grooves milled in the ends (to match the sides) so
the weave gets all locked down tightly at installation.
-
The well pump is turned on the for first time.
Pressurization takes only 30 seconds. So now with water in
the house the mason can do an acid-wash of the chimneys and
fireplaces.
Friday,
April 21st,
2006:
-
The siding on the tower is complete and so is most of the
painting up there. As soon as the last of this is done,
the pump jacks can be removed and no one will ever need to get
up to this height again!
Thursday,
April 20th,
2006:
-
Special aluminum pump jacks are purchased to reach the height of
the 3rd floor tower. These are set on the porch roof and
we can finally reach this area. The siding of this section
begins.
Tuesday,
April 178h,
2006:
-
More paint goes on the siding and the north attic's gable.
Monday,
April 17th,
2006:
-
The first bit of siding paint goes on the dining room.
Friday,
April 14th,
2006:
-
The decorative cedar shingles are complete on the north attic's
gable.
Wednesday, April 5th
thru Wednesday, April 12th,
2006:
-
Out of town for spring break. As usually happens, when the
supervisor is gone, not much gets done.
Thursday,
March 23rd,
2006:
-
The drywall continues with the first floor, garage and tower.
A seventeen-foot high ceiling in the tower presents a particular
challenge.
Sunday,
April 2nd,
2006:
-
Window "hoods" are mill in our shop out of clear, straight-grain
Douglas fir. And due to limited time and equipment, a
local mill shop makes the window hoods the the four
curved-windows.
Wednesday,
March 22nd,
2006:
-
The drywall starts to go up. Most sheets are complete on
the second and third floor.
Tuesday,
March 21st,
2006:
Monday,
March 20th,
2006:
-
The insulation inspection is successful, approved for drywall.
Friday,
March 17th,
2006:
-
The porch roof framing is complete.
-
The insulation is complete.
Monday,
March 13th,
2006:
-
The framing inspection is conditionally successful. We are
given the approval for insulation.
Thursday,
March 9th,
2006:
-
The exterior siding begins with the first five courses of siding
along the front porch. This will allow us to install the
porch outlet required to be in before insulation.
Wednesday,
March 8th,
2006:
-
The exterior doors are installed.
Tuesday,
March 7th,
2006:
-
The new stairs are installed.
-
The exterior doors are re-delivered. They two had to sent
back for rework when they arrived last months with the wrong
sills and trim.
Monday,
March 6th,
2006:
-
All six sections of the oak stairs are re-delivered after being
rebuilt properly with oak stringers.
Monday,
February 20th,
2006:
-
Lots of RG-6 coaxial cable (for satellite) and CAT-6 wire (for
network and phones) are run to all rooms of the house.
Each line is a "home run" from a particular room to a network
interface box in the second-floor laundry room.
Friday,
February 3rd,
2006:
-
The tower top rafter framing is complete.
Monday,
February 6th,
2006:
-
The framing of the tower top continues with that addition of the
plywood.
Wednesday,
January 25th,
2006:
-
The electrical rough-in passes inspection!
Tuesday,
January 24th,
2006:
-
The framing of the tower top begins
Thursday,
January 19th,
2006:
-
The front porch joists are installed. This normally simply
job was complicated by a graceful curved section between the
front and side porch sections. The rim joist was
fabricated on-site by laminating three layers of 1/2 inch
pressure-treated plywood. Before the porch decking is
applied, the porch frame will serve as part of the base upon
which to build the tower top.
-
Electrical rough-in complete.
Wednesday,
January 18th,
2006:
-
The plumbing and gas rough-ins pass inspection!
Tuesday,
January 17th,
2006:
-
The HVAC rough-in passes inspection!
-
Last of the plumbing punchlist items are addressed.
Friday,
January 13th,
2006:
-
The HVAC rough-in is complete.
Wednesday,
January 11th,
2006:
-
The shingling of the main roof is complete.
Tuesday,
January 10th,
2006:
Monday,
January 9th,
2006:
Thursday,
January 5th,
2006:
-
Remaining windows are installed.
Tuesday,
January 3rd,
2006:
-
All first floor windows are installed.
Friday,
December 30th,
2005:
-
The garage roof paper in installed.
-
About 75% of the water plumbing rough in is complete.
Thursday,
December 27th,
2005:
-
The electrical rough-in begins.
Friday,
December 23rd,
2005:
-
The last of the interior walls are framed.
Thursday,
December 22nd,
2005:
-
The shingles arrive.
-
The rafter bracing and kneewalls are complete in the master bath
suite (above garage).
-
HVAC rough-in continues.
-
Several of the windows get installed.
Wednesday,
December 21st,
2005:
-
The stairs are installed
-
HVAC rough-in continues.
-
The basement landing is framed.
Monday,
December 19th,
2005:
Monday,
December 12th,
2005:
-
The HVAC ductwork rough-in starts.
Sunday,
December 11th,
2005:
-
The roof "paper" installed. Actually, we used a roofing
material called
"Titanium-UDL", a synthetic roofing underlayment. This
will stand up to weather longer while we wait for shingles.
It also provides safer footing for the roofers since we have
such an extreme roof pitch (18:12).
Friday,
December 9th,
2005:
-
All of the long (24 foot!) rafters of the garage installed.
-
The dormers for the master bath begin to be framed.
Thursday, December
8th,
2005:
Wednesday,
December 8th,
2005:
-
The rear (interior)
chimney is complete.
-
The main roof is complete and
fully decked with plywood. A temporary roof is built to
cover the opening where the tower will go.
Thursday,
December 1st,
2005:
Wednesday,
November 30th,
2005:
Wednesday,
November 23rd,
2005:
-
Successful throat inspection of master bedroom fireplace.
Monday,
November 21st,
2005:
Friday,
November 18th,
2005:
-
All the roof rafters for the main
ridge are up except for four
left out to allow the masons to set up scaffolding for the
building of the rear chimney.
-
All rafters for the northern
front roof are installed.
-
The hearth foundation
for the fireplace in the master bedroom is poured. This
foundation is wider than the fireplace since it supports a
chimney that has flues
from the family room fireplace (clay) and the basement furnace
and water heater (PVC).
-
The exterior chimney is
complete consisting of one large flue for the study fireplace
and one dummy flue tile. This dummy flue tile will hide 8" metal flue for
the basement's wood stove.
Thursday,
November 17th,
2005:
-
The master bedroom hearth passes inspection.
Wednesday,
November 16th,
2005:
-
The hearth is formed for the master bedroom fireplace.
Weather permitting, the county will inspect Thursday and we'll
pour the hearth Friday.
Tuesday,
November 15th,
2005:
-
More rafters are set.
-
The ceiling above the third floor hall is set to provide an
early platform to work from when building the complex roof
behind the tower.
-
The exterior chimney is
complete up to the eave.
Monday,
November 14th,
2005:
Friday
November 11th,
2005:
-
The main gable
openings are measured for their vents. Due to the
extreme pitch of the roof (18:12), we'll be making custom
louvered gable vents in our shop.
-
The small studio "tower room" walls
are built. This room will have a 17 foot ceiling with
three high windows to let sunlight stream in.
Thursday
November 10th,
2005:
-
The two end gables and
two front gables are
tipped up in place, and it took four men each to lift them.
-
Interior chimneys always present additional challenges with the
requirement to include a fresh-air vent need to supply the
fireplace with adequate combustion air. Getting the
firebox air vent piped to the exterior of the house has
presented a real problem with this house design, but after lots
of head scratching and a consultation with no less than three
inspectors with the county, we hit upon a novel solution.
Building codes allow a fresh air vent near the fireplace
instead of in it, so we're going to install antique Victorian
round floor grates with closable louvers next to the hearth.
The we simply duct these to hidden soffit vents. These
will provide better airflow that the standard in-the-fireplace
air vents and will look very classy.
Wednesday
November 9th,
2005:
-
The gables have their fascias and frieze boards installed.
Triangular openings were cut into the top of the two larger gables
for some custom-made gables vents I'll make in our shop.
-
The exterior chimney continues to climb. Just below the
second floor deck now.
-
The interior chimney (for both the family room and master
bedroom fireplaces) is built up to the second floor deck.
Ready to form for the bedroom hearth. But further work has
stopped until we resolve an issue regarding positioning of the
fresh air vents for these two fireplaces.
Monday
November 7th,
2005:
-
Most windows made these days (even the high-end ones we use)
some with standard window sills that are only about 1-1/4 inches
thick. But most old homes had must more substantial
looking sills. So we custom milled some more historically
appropriate (thicker) window
sills in our own shop based on the engineering drawings from
the window manufacturer.
Friday
November 4th,
2005:
-
All front gables and side gables are fully framed. But
we'll probably install the trim and siding on the end gables
while they are conveniently flat before erecting them.
This will save work up on a ladder or scaffolding.
Wednesday
November 2nd,
2005:
-
Main house roof lumber arrives.
-
Brick and block to complete chimneys arrive.
-
Front gable framing begins.
Tuesday
November 1st,
2005:
-
Dumpster pulled (first load)
-
All the kneewalls for the third floor and attic are built and
stockpiled.
Monday October 31st,
2005:
Friday
October 28th,
2005:
-
Throat inspection for the fireplaces are successful.
-
Third floor wall lumber arrives.
Thursday
October 27th,
2005:
Wednesday
October 26th,
2005:
-
Both the study and
family room Rumford fireplaces are complete
up to the smoke chamber.
Monday
October 24th,
2005:
-
The third floor deck is about done, save for a few sheets of
plywood waiting for one missing floor joist.
-
One of the two 42" Rumford fireplaces on the first floor are
built up to the top of the throat. A throat inspection is
needed before any flue tiles can be set.
-
The fresh air intake for the exterior fireplace must be mounted
to the outside of the chimney, but I hate the ugly aluminum
grill that is normally used. So I asked the mason to set a
"soldier course" of bricks with a fine mesh insect screen behind
it as a more appropriate looking
air intake.
Wednesday
October 19th,
2005:
-
The hearth foundations in the
study and
family room get poured.
-
All but three of the
third floor joists are up.
Due to tall second floor windows, the
header above
these windows must be buried in the third floor deck.
Tuesday
October 18th,
2005:
-
The hearth inspections pass, so we're ready to pour the hearth
foundations.
-
The third floor joists begin to go up.
- A
load of #3 gravel is brought in for the re-graded driveway.
Friday
October 14th,
2005:
Wednesday
October 12th,
2005:
-
The gas tank/lines pass inspection.
-
Hearths are formed up, rebar installed, and flues for the
furnace and water heater are pre-positioned.
Monday
October 10th,
2005:
-
The last of the second floor exterior walls are up.
-
The gas line
from the propane tank is set in the now-shallower
trench and is pressurized for the inspector.
- Foundations
for the
study and family room fireplaces are built.
Thursday
October 6th,
2005:
-
The well trench is partially filled in to safely cover the water
line.
-
As hole is dug and the propane tank is set.
Friday
September 30h,
2005:
Wednesday
September 28th,
2005:
Monday
September 26th,
2005:
-
Framing of the second floor walls
begin.
-
Dominion Power installs meter and begins service.
Friday
September 23rd,
2005:
-
Service entrance (power) inspection successful). This will
allow power company to hook up power.
Thursday
September 22nd,
2005:
-
Waterproof enclosure build around panel box to allow service
entrance approval before house dry-in.
Wednesday
September 21st,
2005:
Tuesday
September 20th,
2005:
-
The garage walls done, except for a small portion over along the
back slab porch.
-
The service entrance (power) installed.
-
Remaining second floor joists over the first floor are complete and are
ready for plywood. The portion of the second floor deck
that extends over the garage is pending arrival of some large LVL (laminated veneer lumber) beams that span the width of
the garage.
-
The well line and well pump power lines installed in trench,
ready for inspection. This same trench will carry the
propane line, though at a shallower depth.
Monday
September 19th,
2005:
-
The garage walls begin to go up.
-
Back porch slab pre-pour inspection successful.
-
The trench from the well to the house has been dug.
Thursday
September 15th,
2005:
Wednesday
September 14th,
2005:
-
Lumber for second floor deck and garage wall arrives.
Tuesday
September 13th,
2005:
-
Dumpster arrives.
-
Excavator installs lines to run the foundation drain and two
independent floor drains to the property edge ("run to
daylight"). This precludes the need for a sump pump.
Monday
September 12th,
2005:
Sunday
September 11th,
2005:
-
Site cleanup day in preparation of final backfilling and grading
tomorrow.
Thursday
September 8th,
2005:
Wednesday
September 7th,
2005:
-
Porch piers are set. They stared up from the pier pad with
cinder blocks, then transitioned to brick before they rose above
final grade.
-
The first floor wall framing begins. The walls are framed
flat on the floor deck, covered with sheathing and wrapped in
Tyvek housewrap before erecting.
Friday
September 2nd,
2005:
Tuesday
August 30th,
2005:
Monday
August 29th,
2005:
Thursday
August 25th,
2005:
Wednesday
August 24th,
2005:
-
The slab prep for the
garage and
basement slabs is done.
During this prep, the flatwork crew installed a second "crock"
for any future sump-pump needs, if they ever should arise.
-
The basement stairs are formed.
-
About 1/3 of the first floor joists
are set. Completing this part of floor framing allows the crew to move to framing the
front porch immediately. This is important so the mason
can build the brick porch piers using the porch frame as a guide
and have perfectly positioned piers.
Tuesday
August 23rd,
2005:
-
The first floor joists are cut to length and ready to set.
Monday
August 22nd,
2005:
-
The subslab plumbing passes inspection.
Friday
August 19th,
2005:
-
The county plumber inspector again fails to show!
Thursday
August 18th,
2005:
-
The county plumber inspector is schedule to inspect the sub-slab
plumbing, but fails to show.
Wednesday
August 17th,
2005:
-
The plumber installs the sub-slab plumbing. This includes
a basement floor drain, a floor drain for the basement walkout
stair landing, basement bath, and an pit to support a future
sewage ejector pump.
-
Porta-John arrives
Monday
August 15th,
2005:
Saturday
August 13th,
2005:
-
The remainder of the sills are set.
Friday
August 12th,
2005:
Thursday
August 11th,
2005:
-
Nine cubes of "Portsmouth Modular"
bricks arrive.
-
The steel beams are set and most of
the sill plates are positioned. The steel company mis-located
the holes that are used to bolt the beams to the lally columns
as well as secure the splice plates. They will have to
send a guy out with a welder to make this right.
-
The remainder of the foundation
drain in complete.
Wednesday
August 10th,
2005:
-
Most of the foundation
drain is
installed and backfilled. The area around the front porch
is left clear due to the access the mason will need to build the
brick porch piers.
-
The
basement steel is set, as is
about half of the green plates (sills).
Tuesday
August 9th,
2005:
-
The foundation is
damp-proofed.
-
The basement
steel arrives.
-
The surveyor performs the wall-check
survey.
Friday
August 5th,
2005:
Thursday
August 4th,
2005:
Wednesday
August 3rd,
2005:
-
Final adjustment day on the wall
forms. We walked the site with the concrete foreman and
addressed several minor tweaks, then agreed upon the depth of
the brick ledge around the perimeter of the house.
Tuesday
August 2nd,
2005:
-
The
remaining
wall forms are placed.
-
The concrete foreman removed a small section of wall to make the
forgotten foot cut for the toilet.
Monday
August 1st,
2005:
-
The
foundation wall forms are
unloaded and begin to
go up. It was noted that the footing cut for the bathroom
toilet was missing, and needs to be cut before the wall pour.
-
The
stone for the base of the
basement slab is placed, as truck access to the basement is lost
once the walls are up.
Monday
July 25th,
2005:
Thursday
July 21st,
2005:
-
The footing forms are installed.
Footing "cuts" are made in the footing my putting a styrofoam
block in the form to keep concrete out of a particular section.
Then once the footing and walls are poured, the foam is easily
chiseled out leaving a passage under the wall where needed to
run any sub-slab pipes.
Tuesday
July 19th,
2005:
-
The
excavation is complete, with the
basement now dug to its full 9 foot depth.
Monday
July 18th,
2005:
-
Finally, we
break ground on the
project. The excavator cuts 75% of the dirt out and
defines the perimeter of the basement and garage.
Friday
June 24th,
2005:
Wednesday
June 22nd,
2005:
Friday
June 3rd,
2005:
-
Health Department site visit.
Wednesday
June 1st,
2005:
-
The last of the dumpsters are hauled
away. Total dumpster count for house removal was eleven.
Saturday
May 28th,
2005:
-
The house site is
staked for a final
review by the Health Department prior to issuance of the
building permit.
Thursday May 26th,
2005:
-
We closed on the property.
-
The old house is successfully
demolished. So far five dumpsters are loaded and being
slowly hauled away.
Monday
May 23rd,
2005:
-
We receive the demo permit.
Wednesday
May 18th,
2005:
-
We finally received
the certification letter for the proposed drain field.
Tuesday
May 17th,
2005:
-
The old overhead power wire to the
old house is removed by Virginia Power. This is a
prerequisite to being given a demolition permit.
Tuesday
May 10th,
2005:
-
We received preliminary approval of
the certification letter for the proposed drain field.
We're expecting the formal approval any day now.
Monday
May 9th,
2005:
Thursday
May 5th,
2005:
-
The blueprints are submitted to the
building department for approval.
Monday
May 2nd,
2005:
-
The final plat showing the surveyed
drain field area is received by the health department. They
indicate that all looks good and after a final site visit to see
the stakes, we should have out drain field certification letter
by week's end.
Tuesday April 26th,
2005:
-
The yield test
and chemical analysis tests come back. The chems are clean and
the yield test revealed a rate of 4.2 GPM. This is twice what
we expected and four times the minimum.
Saturday April 23rd,
2005:
-
The yield test
is performed on the well to establish the well’s yield. Water
is pumped out continuously for around a number of hours while
every fifteen minutes a one gallon bucket is filled and timed to
see how many seconds it take to fill it. This test is repeated
until the time to fill a bucket levels off. That rate is the
established yield. For a well to be approved, it must have a
yield of at least 1 gallon per minute.
Wednesday April 20th,
2005:
-
The soil
scientist meets with the health inspector to review the site
and dig an additional test hole.
Monday April 18th,
2005:
-
The well
company installed the well pump and drew a sample of water to
send out for chemical analysis.
Wednesday April 13th,
2005:
-
The property
survey is complete and delivered showing the newly laid-out
drain field and 2 foot contour lines. The topographic lines will
let the health department access the new drain field sighting.
Wednesday April 6th,
2005:
-
The steel
casing of the new well has been grouted to bedrock.
-
With a health
department inspector in attendance, the old well is grouted
shut. This was a requirement of the real estate contract and a
prerequisite to tearing down the old house.
Monday, March 28th,
2005:
-
Well drilling
continues. Six inch bore taken down to total depth of 400
feet. Flow test indicates at least 2 gallons per minute of
water.
Saturday, March 26th,
2005:
-
Major site
cleanup day. Lots of debris and brush removed. We burned what
we could, everything else went into dumpsters.
Friday, March 25th,
2005:
-
Well drilling
begins. Holes drilled to 107 feet and 8” steel casing
installed.
-
Dumpsters
arrive for tomorrow’s cleanup day.
Thursday, March 24th,
2005:
-
The
well
drilling rig arrives and gets set up. Not an easy job
considering the slope of the back corner where the well is to
go.
-
The existing
well line is removed from the old soon-to-be-abandoned well.
Wednesday, March
16th, 2005:
-
Fill dirt
removed from proposed drain field site.
-
Path cleared
for access to well site by drill rig.
|