|
Monday, August 2nd, 2004
-
Walk-thru
with minimal punchlist items
-
Closing
with new owner
Wednesday, July 28th, 2004
-
Received
Occupancy Permit from the county
Tuesday, July 27th, 2004
-
Successful
building inspection
-
Successful
electrical inspection
-
Successful
plumbing inspection
Monday, July 26th, 2004
-
HVAC
punchlist worked through
-
Final
prep for electrical final inspection tomorrow
-
Hearth
slate set
-
Carpet
installed
-
Kitchen
faucet operational
Sunday, July 25th, 2004
Saturday, July 24th, 2004
-
Last
of kitchen cabinets get installed
-
Upstairs
pedestal sinks installed
-
Gas
cooktop installed
Friday, July
23rd, 2004
-
Granite
countertops installed
-
Final
building inspection…two small punchlist items to address
-
Successful
final mechanical (HVAC) inspection
Saturday, July 17th, 2004
-
Last
of outlets installed
-
More
fans and lights installed
Friday, July 16th, 2004
-
Final
coat of interior painting started
-
Cornice
work for patio ceiling installed
Monday, July 12th, 2004
-
Countertop
measurement taken.
-
Last
of upstairs trim varnishing complete.
Sunday, July 11th, 2004
-
Kitchen
base cabinets set.
Friday, July 3rd, 2004
-
Jack
and Jill bath floor tile grouted.
All tile complete.
Friday, July 2nd, 2004
-
Brush
removed and ready for hydroseeding in the upper meadow.
-
Stained
doors get their first coat of varnish.
-
Bedroom
2 (and several other windows) get stained.
-
Jack
and Jill bath wall tile set and grouted.
-
Jack
and Jill bath floor tile set and ready for grout.
-
Several
fans and light fixtures installed.
Thursday, July 1st, 2004
-
Interior
doors get their cherry stain applied.
Gorgeous!
Wednesday, June 30th, 2004
-
All
master bath tile set and grouted.
Tuesday, June 29th, 2004
-
Jack
and Jill bath tub installed.
Sunday, June 27th, 2004
-
Interior
oak trim complete upstairs.
Thursday, June 10th, 2004
-
Completed
interior wall painting (first coat).
Monday, June 7th, 2004
-
Completed
exterior painting.
Friday, June 4th, 2004
-
Completed
dip-painting of the porch railing spindles.
-
Continued
exterior painting. Ivory trim
almost complete.
Sunday, May 30th, 2004
-
Continued
to dip-paint the spindles.
-
Installed
antique door locks on all exterior doors.
-
Interior
trim continuing. Bedroom 2
complete, master bedroom has all baseboards done.
Monday, May 24th, 2004
-
Phone
line installed from pedestal.
-
Special
drain set to divert driveway runoff.
Sunday, May 23rd , 2004
-
Continued
to dip-paint the spindles.
Saturday, May 22nd, 2004
-
Installation
of oak interior trim begins.
-
Started
to dip-paint the 102 turned porch spindles.
Friday, May 14th, 2004
-
First
coat of exterior painting completed.
Some parts (attic dormers, porch ceilings) have both coats
completed.
Wednesday, May 12th, 2004
-
Oak
floor completed.
-
Grass
seed sprouting nicely.
Thursday, May 6th, 2004
Tuesday, May 4th, 2004
-
Oak
floor continues on first floor.
Kitchen
better than halfway done.
-
Hunt
Country Hydroseeding preps the site for seeding.
-
Davenport
installed the
basement
insulation.
Monday, May 3rd, 2004
-
Oak
floor begins on first floor.
Parlour
and hallway mostly done.
-
Remaining
oak floor arrives
-
Oak
fluted door/window casing arrives
Sunday, May 2nd, 2004
-
The
household water system is pressurized…no leaks.
Friday, April 30th, 2004
Wednesday, April 28th, 2004
-
The
exterior
painting begins.
-
The
nest of an Eastern Phoebe (Myiarchus tyrannulus) is discovered above a
light fixture in the porch floor above the patio. We’ll monitor the next and hold off on
installing the patio ceiling until the eggs hatch and the nestlings
fledge.
Wednesday, April 24th, 2004
-
Mulch
bed around house placed.
Monday, April 19th, 2004
-
One
small section of the house get first
test
coat of color. They look
great!
Thursday, April 15th, 2004
Tuesday, April 13th, 2004
Tuesday, April 6th, 2004
Saturday, April 3rd, 2004
-
Lots
more outlets installed.
Thursday, April 1st, 2004
Tuesday, March 30th, 2004
Monday, March 29th, 2004
-
Most
of exterior wood trim
caulked.
Tuesday, March 23th, 2004
-
Wall
priming touched up
-
Final
ceiling coat of paint applied
-
Heat
turned on full time now to begin wood flooring acclimation
Saturday, March 20th, 2004
-
Driveway
gets a bit more tweaking
-
Oak
flooring arrives
-
A/C
units set and plumbed
Friday, March 19th, 2004
Wednesday, March 17th, 2004
-
Primer
shot onto interior walls
Tuesday, March 16th, 2004
-
Driveway
gets it stone laid and graded
-
All
windows and doors taped in preparation for interior wall priming
Friday, March 12th, 2004
Tuesday, March 9th, 2004
Saturday, March 6th, 2004
-
With
the drywall hung, we’ve started to install switches and begun to bring
light to the house.
Friday, March 5th, 2004
Wednesday, March 3rd, 2004
-
Second
coat of
drywall
mud goes on.
-
Rough
grading around septic tanks complete.
-
Started
to fill the septic tank.
Tuesday, March 2nd, 2004
-
Drywall
hung in garage and basement
-
Final
plumbing connections of septic system complete
-
Power
lines for septic system set in trench.
-
Well
wiring complete. We have water!
Monday, March 1st, 2004
-
Taping
and mudding of
drywall
starts (first coat)
Saturday, February 28th, 2004
-
Drywalling
starts. All drywall hung on 1st
and 2nd floors.
Friday, February 27th, 2004
-
All
septic plumbing is connected. Ready
for wiring.
-
Drywall
is delivered.
-
In-ceiling
speaker wires installed
-
All
backer-boards for towel bar and toilet paper holder installed.
Wednesday, February 25th, 2004
Monday, February 23th, 2004
-
The
septic field install begins with the setting of the
Infiltrator
chambers.
Thursday, February 12th, 2004
-
The
foundation along the front porch
get covered with the
brick
veneer that Greg cut earlier.
Wednesday, February 4th, 2004
-
Front
door installed. The side lights
were damage in shipping from vendor to distributor, so replacements are
pending.
-
Back
doors (garage and porch) are installed.
Saturday, January 30th, 2004
-
Furnaces
test fired sucessfully. Will turn
on full time when doors and 2nd floor ceiling are in place.
January 16 thru January 29th
·
Components
of chambered septic field deliverered.
·
Remainder of back porch
metal roofing completed.
Thursday, January 15th, 2004
Wednesday, January 14th, 2004
Tuesday, January 13th, 2004
Monday, January 12th, 2004
Thursday, January 8th, 2004
-
The
roof
tin has been installed on the front porch, bay windows, and cornice
returns. The back porch roof is in
work.
Tuesday, January 6th, 2004
Monday, January 5th, 2004
-
Insulation
inspection completed successfully.
-
The
beadboard
ceiling for the back porch is complete.
Sunday, January 4th, 2004
-
Gregg
uses a brick saw and cuts
brick
veneer for the front porch foundation.
-
Water
heater and lower furnace
flues
are tied into dedicated flue set into chimney. This was done to minimize the modern looking protrusions
through the house walls.
Saturday, January 3rd, 2004
-
Gregg
begins to thin out the underbrush in the
south
yard. It opens up a nice view
of the house from the road.
Friday, January 2nd, 2004
Thursday, January 1st, 2004
-
Last
minute insulation items completed for inspection Monday
-
All
video, phone, and network wiring roughed in to the home
network
box.
Monday, December 29th, 2003
-
Tongue
& Groove fir porch
floor
boards installed on rear porch.
Tuesday, December 23th, 2003
-
Wall
(and cathedral ceiling)
insulation
installed. I’m not entirely happy
with several items regarding the work, so we’ll get the insulators to fix
them before we call the county for an inspection.
Sunday, December 21th, 2003
Saturday, December 20th, 2003
-
Mason
set the two
piers
for the pergola
-
Began
puling all phone, network, and video cables.
Friday, December 19th, 2003
-
Framing
inspection passed.
Thursday, December 18th, 2003
-
Electrical
rough-in inspection passed.
Tuesday, December 16th, 2003
Monday, December 15th, 2003
Saturday, December 13th, 2003
-
Fix
of electrical items for rough-in.
Friday, December 12th, 2003
Thursday, December 11th, 2003
-
Top
section of
oak
staircase installed. A lot of
fussing was needed to get the stingers of the upper and lower sections
lined up nicely.
Wednesday, December 10th, 2003
-
Electrical
rough-in inspection. Minor punch
list of fixes needed.
Thursday, November 27th, 2003
-
Minor
wrap up work on electrical rough-in.
Wednesday, November 26th, 2003
Saturday, November 22nd, 2003
-
Work
on electrical rough-in continues.
Wednesday, November 19th, 2003
-
Chimney
almost complete. Half a dozen more
courses to go.
Saturday, November 15th, 2003
-
Work
on electrical rough-in continues.
Monday, November 10th, 2003
-
Lower
section of oak staircase is set.
Upper section is tricky so we’ll wait until I can coordinate with
chief carpenter to perform this operation himself.
-
Siding
continues.
Friday, November 7th, 2003
-
Front
view
-
Chimney
continues to climb slowly. There
are a number of “corbels” where the brick steps out several inches over
3-4 courses. When these courses
are set, if weight is set on them before the mortar set, the bricks will
roll out and collapse. So when
ever new corbel is set, work must stop until at least the next day. It made for slow work, but a stunning
chimney.
Thursday, November 6th, 2003
Wednesday, November 5th, 2003
Tuesday, November 4th, 2003
-
Exterior
trim and siding installation begins.
-
The
first part is the “water
table”. This is a 12 inch
board that wraps the entire house and provides an architectural “base” for
the siding. This is a component
you don’t see much anymore, but was the norm in better quality older
homes. It overlaps the
intersection between framing and brick foundation and is capped with a
drip edge to shed water. This drip cap has a bead along the top that
proper kicks out the first course of siding so we don’t need to apply an
extra shim. This drip cap is one
of the very few place that we choose to use a plastic material due to the
high water exposure it gets.
Monday, November 3rd, 2003
Sunday, November 2nd, 2003
-
Electrical
work continues. First power flows
in the house as each floor is given a temporary circuit to run the power
tools and work lights.
Friday, October 31th, 2003
Thursday, October 30th, 2003
-
Service
inspection successful.
Tuesday, October 28th, 2003
-
Chimney
construction begins. Brick
completed up to the height of the smoke chamber, just above the firebox.
-
Roof
shingles arrive
-
Lower
patio posts set
Monday, October 27th, 2003
-
HVAC
rough-in inspection successful
-
Last
of the windows are installed
Saturday, October 25th, 2003
-
Electrical
rough-in work continues
Friday, October 24th, 2003
-
Oak
staircase arrives
-
Power
line trench is backfilled
Thursday, October 23rd, 2003
-
Rumford
fireplace built
-
NOVEC
installs power line from power pole to meter box. The meter itself will not be set until
a “service entrance” inspection.
Wednesday, October 22nd, 2003
Tuesday, October 21th, 2003
-
Brick
arrives for chimney
-
Minor
plumbing rough-in items fixed
Monday, October 20th, 2003
-
Power
line trench inspected successfully by NOVEC
Sunday, October 19th, 2003
-
Power
line trench completed
Saturday, October 18th, 2003
-
Lots
more wiring completed
Friday, October 17th, 2003
-
Back
porch roof sheathed
-
Power
line for NOVEC started
-
Chimney
foundation formed, inspected, and poured. The wood in the center are two-by-fours placed to hold open
a hole for the ash dump.
Thursday, October 16th, 2003
-
Gas
inspection - passed
-
Plumbing
inspection – failed for 2 minor punchlist items
-
HVAC
inspection – failed for 5 minor punchlist items
-
Fireplace
foundation wall set and furnace/water heater flue elbows set
Wednesday, October 15th, 2003
-
Rumford
fireplace package arrives
Tuesday, October 14th, 2003
-
Gas
rough-in complete
-
Plumbing rough-in complete
-
All
but a few windows installed
Monday, October 13th, 2003
-
Front
gable trim complete and gable window set.
-
Plumbing
and gas rough-in continues
-
Electrical
panel
box wiring starts
Saturday, October 11th, 2003
-
Wiring
continues
-
Work
on
cornice
continues.
-
We
routed the
bathroom
vents to tiny inconspicuous inverted vents mounted flush in the
soffit. We wanted to avoid, where
possible, ugly wall-mounted vent exits.
-
Most
of the HVAC rough-in is complete.
The very accommodating HVAC contractor installed custom-made
register
boxes mounted below the first floor to allow me to install antique
floor heating registers. I use
these in my own home and they look and work great. It’s all in the details.
Friday, October 10th, 2003
Thursday, October 9th, 2003
-
Basement
stairs set. I’m not happy with the fit due to the height of the
landing, so we’re going to remove the bottom half of the stairs, lower the
landing, and reset them.
-
Propane
trench filled in.
Wednesday, October 8th, 2003
Tuesday, October 7th, 2003
Monday, October 6th, 2003
-
Propane
line is set and pressurized to check for leaks.
Saturday, October 4th, 2003
-
Electrical
rough in work begins. Most wires
pulled and boxes set on second floor except for overhead lights.
-
Plumbing
work continues with most of the major work done.
Friday, October 3rd, 2003
-
Cornice
work continues with the carpenters are working counterclockwise around the
house, leaving a
5
foot gap where the chimney will be built.
-
Propane
tank gets buried and the gas line trench is dug.
Thursday, October 2nd, 2003
-
Work
begins on the cornice, starting at the back side of the house over the
garage.
-
Plumbing
rough-in begins.
Tuesday, September 30th, 2003
Saturday, September 2thth, 2003
-
Minor
work continues on HVAC rough-in.
Will complete in two weeks when flues are installed and first floor
heat register boxes are set.
Wednesday, September 24th, 2003
-
The
rear dormer is built.
Tuesday, September 23th, 2003
Saturday, September 20th, 2003
-
The
majority of the upper HVAC rough-in is complete. This includes routing the
flue
for the upper furnace out the side of the rear dormer. Due to the layout of the house on the
lot, this dormer is almost invisible so it can be used to hide such things
to minimize modern roof protrusions.
Wednesday-Friday, September 17th -
19th , 2003
-
No
progress as we all stand down for Hurricane Isabel.
Monday, September 15th, 2003
-
The
roof paper is finally on.
Friday, September 12th, 2003
-
The
sheathing
of the roof is complete. Ready for
roofing paper.
Thursday, September 11th, 2003
-
The
sheathing of the
main
roof is almost done complete.
All that remains is some plywood over the master bedroom and some
stick framing over the master bath.
-
The
power
pole is set in line with an existing power line that cuts across the
back yard.
Monday, September 8th, 2003
-
The
blocking and sheathing begins on the
main
roof.
Saturday, September 6th, 2003
-
The
blocking and sheathing is complete on the
garage
roof. Ready for roofing paper.
-
The
lower
furnace is set and the main HVAC trunk lines are installed. The furnace is tucked under the
basement staircase so the main supply plenum above the furnace was
fashioned with a
sloped
top to fit.
Friday, September 5th, 2003
-
The
power
pole (to be set in the back yard) is delivered.
Monday, September 1st, 2003
-
The
blocking begins on the garage roof.
Tuesday, August 26th, 2003
-
The
largest
trusses were lifted by crane and set.
Smaller ones will be set later as the main trusses are aligned and
blocked.
Thursday, August 21th, 2003
-
The
trusses were moved by hand up onto the property and the crew began sorting
them and
pre-assembling
some pieces in preparation for setting into place next week.
-
The
second floor
walls
are aligned with reference lines and braced in place prior to setting
the trusses.
Wednesday, August 20th, 2003
-
The
trusses were delivered, but since the truck could not get into the
driveway (it was a 42 foot semi), the bundle of trusses were left along
the
side
of the road! This was not
noticed until the next morning.
Monday, August 18th, 2003
Saturday, August 16th, 2003
-
A
phone line was found awhile ago that ran across the property blocking the
driveway from being cut down to the proper grade. After finally getting hold of a Verizon
engineer, I received permission to excavate and re-bury the cable deeper
to allow the drive excavation. So
VERY carefully, Dale (the carpenter who also owns a skid-steer) dug a
deep
trench next to the cable. We
then hand dug the cable out of the side of the new trench and set it at
the bottom, then refilled the hole.
-
Slabs
did not get poured Friday, reasons unknown.
Thursday, August 14th, 2003
-
Front
porch slab pan inspected, ready for pour tomorrow.
Wednesday, August 13th, 2003
-
Second
floor framing completed.
-
Garage
walls complete.
-
Garage
truss-supporting ledger board anchored to wall.
Tuesday, August 12th, 2003
Monday, August 11th, 2003
-
Front
porch pan formed for pouring the slab. The carpenters had to relocate their
temporary
supports to hold up the second floor.
Since we are low on soil, we didn’t want to waste it to fill in the
porch cavity. So the flatwork contractor
spanned the porch with 16 gauge corrugated steel sheets to provide the
base for the slab. A side benefit
here is this allows the homeowner to punch a doorway in the basement wall
to build a fully concrete-encased room suitable for a wine cellar or
tornado shelter.
-
Rear
patio slab formed.
-
Second
floor wall framing continues.
Friday, August 8th, 2003
Thursday, August 7th, 2003
-
Second
floor deck complete. The kitchen
has “clipped wall” for architectural purposed and to allow more room on
the back porch. But the bedroom
above it has a normal squared-off corner that overhangs the kitchen
window. This little trick is
easily performed by running a
large
header off the second floor corner out to be held up by the porch
columns and all this framing is nicely concealed in the porch ceiling.
Wednesday, August 6th, 2003
-
All
joists positioned except for a handful over kitchen nook.
Tuesday, August 5th, 2003
Monday, August 4th, 2003
-
Minor
first floor wall punchlist items fixed.
-
Second
floor deck installation with positioning of
large
header over front porch
Saturday, August 2nd, 2003
-
Last
of the first floor interior walls go up.
-
Last
of foundation brickfacing completed.
Friday, August 1st, 2003
-
Last
of the first floor interior walls go up.
-
All
foundation brickfacing completed except front wall and around chimney
Thursday, July 31st, 2003
Wednesday, July 30th, 2003
Tuesday, July 29th, 2003
Monday, July 28th, 2003
-
First
floor deck construction continues with the installation of the last of
the joists and the start of the plywood.
-
The
joists are wood I-beams, which are stiffer and more stable that similar
sized dimensional lumber. Its
design make it very strong under bending loads. However, it is not designed for downward compression
loads. So all along the perimeter
of the house, directly below any load-bearing wall above, the joist has “squash
blocks” nailed to each side to properly hold the load from above
without squeezing the joist.
-
While
often left out by modern builders, I always install wooden “cross-bracing”
between the joists in a row down the middle of the floor. Being diagonal, they help stiffen the
floor by allowing any single load on a joist be shared by the joists on
either side of it. It also helps
prevent twisting of the joists.
They get nailed to the top flange of the joists, then after the
entire floor is constructed, we go underneath, push the cross-brace up
tight and nail the bottom. Old fashioned, yes, but I like a VERY solid
floor.
Friday, July 25th, 2003
-
Load-bearing
wall behind stairs framed.
This wall, like the walk-out wall will support floor joists in
conjunction with the foundation walls.
-
Living
room floor joists set.
-
Dining
room floor joists set.
Thursday, July 24th, 2003
Wednesday, July 23rd, 2003
-
First
floor deck framing begins.
Lots of time is spent establishing reference lines to which the
first floor deck is framed. This
is critical because all the house wall positions are based on an accurately
sized and positioned first floor deck.
-
Began
setting rim joists.
-
Began
setting main joists.
Tuesday, July 22nd, 2003
Monday, July 21st, 2003
-
Remainder
of the
sills
set.
-
Garage
slab pre-pour inspection – passed.
-
Basement
slab pre-pour inspection – passed.
Saturday, July 19th, 2003
-
Basement
slab prep complete. Consists
of a simple 4” slab with two small areas “thickened” to provide some
load-bearing wall support.
-
Garage
slab prep complete. Consists
of a 4” slab with two integral “grade beams”, which are simply two “ribs”
cast into the bottom to help stiffen the slab. While the slab is cast upon fill dirt, that fill will
eventually sink and the slab will be supported by a ledge precast into the
side foundation walls of the garage.
Friday, July 18th, 2003
-
Garage
backfilled to allow garage slab prep.
-
Rough
grading/backfilling performed, except where the driveway first enters
the property. We found an
unmarked, active phone cable that need to be lowered several feet to allow
proper grading of driveway entrance.
-
Steel
beam set.
-
Carpenter
begins setting
sill plates.
Wednesday, July 16th, 2003
-
Subslab
inspection – passed.
-
Back-fill
inspection – passed
-
Well
line and pump lowered into well
-
Steel
beam delivered
-
Met
with excavator to work details of rough grade elevations.
Tuesday, July 15th, 2003
Monday, July 14th, 2003
Friday, July 11th, 2003
-
Forms
removed. The brick ledge can be
clearly seen here. The large gap
in the wall is were the basement floor is at grade and will provide
walk-out access to a patio under the porch. This opening will be framed with lumber once the basement
slab is poured.
-
View
Thursday, July 10th, 2003
Wednesday, July 9th, 2003
-
Form
setup complete. All that remains
is to prepare for the “brick ledge” which will be done the morning of the
pour. The outer face of the wall
will step back 4” to allow courses of brick to be set from the ledge up to
the top of the wall. The
positioning of the ledge is based on how high up the wall the grade is
expected to be, so brick is only used where the foundation will show. This ledge is formed by first forming
the walls to the final thickness.
Then either a wooden form or large sheet of Styrofoam is placed in
the main forms where the brick will go to displace the concrete. When the forms are removed, the
Styrofoam is chipped away leaving a stepped edge for the brick.
-
View
Tuesday, July 8th, 2003
-
Concrete
wall form setup begins.
Wednesday, July 2nd, 2003
Tuesday, July 1st, 2003
-
Footings poured. The strip
down the center of the footings is a “key” to help the wall lock to the
footing and resist sliding sideways when backfilled.
-
View
Monday, June 30th, 2003
- Footing work complete. The dirt
inside the forms has been further excavated by hand to provide a smooth
level surface before the pour. The
dirt removed is placed outside forms to prevent concrete leakage under
forms.
-
View
Friday, June 27th, 2003:
-
Footing work begins. Forms
are placed first to define the edges of the footings.
-
View
Wednesday, June 25th, 2003:
-
Excavated for basement and garage
Saturday, June 21st , 2003:
Wednesday, May 28th, 2003:
- Closing on land on Garnet Road
|
|