Construction Journal of the Slater Road Project

   

Last updated: 4/11/2001

Here’s the progress, with most recent work listed first.

 
Tuesday, April 10th, 2001
  • Today’s full view: View 1
  • Window heads are being made up on site from the same crown molding used under the eaves.
  • Siding complete on kitchen and Emily’s room.
  • Second half of the 2200 board-feet of poplar is on its way to the kiln. Thanks, Gregg!

Sunday, April 8th, 2001

  • By now, all long rafters are up, about 30% of ceiling joists and 6 sheets of plywood. Still to do: rear hip rafter, all jack rafters, remaining plywood and ceiling joists.

Thursday, April 5th, 2001

  • Rafters start to go up. All full rafters on north end installed.

Wednesday, April 4th, 2001

  • Last of the columns and beams are up on the wrap-around porch, as are temporary railings.

Tuesday, April 3rd, 2001

Monday, April 2nd, 2001

  • Three more columns go up, and all the beams for the erected columns.
  • One thousand board-feet of sawn poplar is hauled off to the kiln for drying. This will eventually end up as casing, baseboard, crown molding and kitchen cabinets.

Sunday, April 1st, 2001

  • Work on the wrap-around porch begins with the arrival of my father. Together, we get the first six columns up and one segment of beam.

Wednesday, March 28th, 2001

  • The roof is finished (almost). The roofing is multi-tone black Architectural (dimensional) shingle. The flat roof over the service porch is hand-crimped standing seam metal. The roof well for the guest room window is copper with soldered joints. All that is left is the shingles for the four of cornice returns.

Sunday, March 25th, 2001

  • Met with the plumber and did the layout for the house. We’ll use heavy wall copper pipe for supply lines and a combination of PVC and cast iron for the DWV (drain-waste-vent). The cast will only be used where there are vertical runs from the second floor to keep the noise suppressed.

Thursday, March 22nd, 2001

Wednesday, March 21st, 2001

  • Upper section of main staircase re-set. But due to improper sizing by the manufacturer, this adjustment won’t work. Now the stair treads are notably tilted!
  • Half wall along stairs in the sewing room built.
  • Chimney in sewing room boxed in.
  • Downstairs windows arrived. These are the old-style windows with brass chains and sash weights.
  • The first of the shop tools delivered. Includes a 12.5 inch thickness planer and 6x47 inch jointer. These will be needed to make the kitchen cabinets and raised panels for the foyer and study. A 1.5 HP shaper is due next week.

Tuesday, March 20th, 2001

Monday, March 19th, 2001

  • Took lots of stair measurement and plotted the data out with Microsoft Excel. It helped illustrate just how the upper section of the main stairs are mis-sized.

Saturday, March 17th, 2001

  • Examined the main staircase with Dale and discovered that it was installed improperly. One step didn’t account for the finish floor thickness on the landing so we’re off by ¾ inches! Dale will fuss with Monday.
  • Entire second floor electrical rough-in complete!
  • Installed small (30A, 2 circuit) sub-panel in woodshop and wired up four wall outlets for power tools.

Friday, March 16th, 2001

  • Roofing of main house complete.
  • Well, it’s the end of the week and the 1st floor windows promised this week never showed up.

Thursday, March 15th, 2001

  • The roofing started (rear side) but had to stop due to rain.
  • Entire main porch deck framing complete.

Tuesday, March 13th, 2001

  • Reviewed hearth with mason. He made it three inches narrower on each side. To accomplish this he ripped six inches off the center piece of slate. Looks all wrong, and he will reset it the full width.

Monday, March 12th, 2001

  • Last footing for service porch poured. Ash cleanout door installed. Slate hearth set. All but 4 steel beam pockets in foundation sealed up with mortar.
  • Rear section of porch deck is framed.

Sunday, March 11th, 2001

Saturday, March 10th, 2001

  • Lower section of main stairs removed and landing lowered 8". A triangle section was added to bring part of landing up to original height.
  • Main porch piers still in work. Some were thought to be done only to discover they were too short. The mason had the wrong reference point from which to measure. Four more courses of brick will work nicely.
  • Table saw and mini-workbench brought into woodshop.

Friday, March 9th, 2001

Thursday, March 8th, 2001

  • "Winder" landing solution chosen for main staircase. Stair manufacturer blessed this idea and will ship us an extra riser and tread nosing to accomplish this.
  • Eaves completed on rear bump-out (family room).

Tuesday, March 6th, 2001

  • Basement stairs set successfully.
  • Main staircase installation, but not so successfully. The lower segment and landing was installed, but insufficient headroom was provided for by the stair supplier. He took lots of measurements but simply goofed somewhere. In his setup, there are 6 steps to the landing and then 9 more to 2nd floor. But those 6 lower treads cause the steps to stick out into the foyer a bit too far and the tread under the edge of the ceiling opening is only 6’-4" above the steps (should be 6’-8"). One solution is to lower the landing, remove one tread from the lower segment, and add a "winder" to the landing. That will keep the upper (expensive) segment from needing to be rebuilt.
  • Main porch piers have been started.

Sunday, March 4th, 2001

  • More electrical wiring. Getting close to completing.
  • Trim work on garage gable finished.

Wednesday, February 28th, 2001

  • Service porch framing completed.

Tuesday, February 27th, 2001

Monday, February 26th, 2001

Saturday, February 24th, 2001

  • Chimney built up to roof deck.

Friday, February 23rd, 2001

  • Fireplace boxed-in in the family room.
  • Lower segment of the laundry chute built.
  • Lighting established on 2nd and 3rd floor.

Thursday, February 22nd, 2001

Wednesday, February 21st, 2001

Tuesday, February 20th, 2001

  • Built the two wide front porch piers.
  • Last of the materials (fire brick, sand, flue tiles) arrive for the building of the fireplace tomorrow.

Sunday, February 19th, 2001

  • Finished the ductwork rough-in.

Saturday, February 18th, 2001

  • Wired up the lighting in the basement.
  • Installed ductwork in the wood shop to heat/cool the lower kitchen.

Thursday, February 15th, 2001

Wednesday, February 14th, 2001

  • Had the electrical rough-in inspection. Lots of items he wants done but nothing unexpected.

Tuesday, February 13th, 2001

Monday, February 12th, 2001

  • Third floor windows set.
  • Roof papered. Technically, we are now "dried-in".
  • Miscellaneous framing punchlist items fixed.

Sunday, February 11th, 2001

  • My friend Gregg and I worked all day to finish (almost) the 3rd and 1st floor wiring. Some minor items to deal with, and the basement needs lights, but I’m pressing ahead for an electrical rough-in inspection on Tuesday.

Saturday, February 10th, 2001

  • Today’s views: View 1, View 2
  • Upper heating ductwork install started.
  • Third floor wiring started.

Friday, February 9th, 2001

  • POWER! After months of paperwork and delays, we have power. Gentlemen, do NOT start your generators.
  • Second floor windows installed.

Thursday, February 8th, 2001

  • Northern Virginia Electric Co-operative finally starts work. A power pole is send way down the front yard with a transformer. A trench for the buried power line is dug from the pole to the rear of the house where I installed the meter box. The buried cable was laid and mostly filled in.
  • Electrical rough-in of second floor 100% complete.

Wednesday, February 7th, 2001

  • The second floor, third floor and garage windows arrive.
  • All components for the Rumford fireplace arrive.

Monday, February 5th, 2001

  • Six loads of #3 gravel spread as new base for driveway.
  • Rear gable framed and ready for paper.
  • Garage "clipped-gable" framed and ready for paper.

Sunday, February 4th, 2001

  • Lots more wiring complete this weekend.

Friday, February 2nd, 2001

  • Dormer roofs framed. Top roof ready for paper.

Thursday, February 1st, 2001

  • Fireplace materials and 2/3rd of the windows delivered, but couldn’t get up the driveway due to massive mud ruts in driveway. The snow-melt and rain have sunk the undersized base gravel. Need lotsa #3 gravel and FAST!
  • Dormer walls framed.
  • 3rd floor knee walls framed.
  • Measured for staircases.

Monday, January 29th, 2001

  • All sheathing complete on front roof surfaces.
  • Completed second floor wiring, except for the bathrooms.

Sunday, January 28th, 2001

Saturday, January 27th, 2001

  • All (well, most) stud holes drilled for wiring.
  • Started to pull wires on the second floor.

Tuesday, January 23rd, 2001

Wednesday, January 17th, 2001

Tuesday, January 16th, 2001

  • Last of gable trim installed.
  • With the help of a crane, the rear gable over the family room was lowered into place.
  • Then the north gable and south gables were erected.
  • Lastly, the steep front gable was erected.
  • The ridge beam (made up of several 1.75 x 14" microlams nailed together) was lowered and supported and stabilized with four temporary rafters.
  • All trusses over garage and lower kitchen were set.

Monday, January 15th, 2001

  • Garage walls were erected and trued up today.
  • The second floor deck was corrected for the laundry chute.
  • Pulled 3 more circuits. Twelve circuits wired up. Just about done the breaker box.

Sunday, January 14th, 2001

  • Almost completed the north gable, south gable, and front gable. Only minor trim to complete before raising.
  • Garage walls framed. Will tip up on Monday.
  • All basement ductwork in place except for ducts under lower kitchen. This will require a 9x13 inch hole cut into concrete wall, and the mason says he can do this Monday. Ductwork for 2nd and 3rd floor will wait until dry-in.
  • Pulled nine 2nd and 3rd floor circuits. I’ll wire them up Monday night.

Saturday, January 13th, 2001

  • Framing of three main roof gables complete. Interior trim being installed.
  • All foundation brickfacing complete. Looks great! The corner brick in the second course is a brick from the original Sugar Bowl stadium. This hold lots of sentimental value, as the Sugar Bowl was the stadium of my Alma Mater, Tulane University.
  • HVAC guys arrive to start heating install. All first floor holes cut to use my antique floor registers.
  • Mason completed all brick facing of exposed foundation.

Thursday, January 11th, 2001

  • Completed 3rd floor deck. Quite a view from up there from West, South, East, and North.
  • Began to frame three main roof gables. Will install most exterior trim first, then use a crane to tip them up in place.
  • Mason faced the rear of house foundation with brick.
  • Wired up the main run of 3 more circuits.
  • HVAC folks deliver ductwork.

Tuesday, January 9th, 2001

  • Wired up the main run of the first 8 circuits.

Saturday, January 6th, 2001

  • Last of 3rd floor joists installed and most plywood placed. Ran out of plywood so will continue Monday.

Wednesday, January 3rd, 2001

  • Hearth inspection successful. Mason must tweak the re-bar position slightly to accommodate the basement furnace flue and the ash door, but otherwise he’s ready to pour the fireplace slab when we get a warm day.
  • Most 3rd floor joists set. Need another beam member for stair opening and then last of joists can be set. Expect this and plywooding on Friday.

Tuesday, January 2nd, 2001

  • The mason prepped the top of the chimney foundation for the fireplace/hearth slab. Inspection called for tomorrow.

Monday, January 1st, 2001

  • I mounted the main and auxiliary circuit breaker panels on the side of the chimney foundation. I then tied them into the main service entrance.

Sunday, December 31st, 2000

Friday, December 29th, 2000

Thursday, December 28th, 2000

  • All interior and exterior second floor walls are complete. Just a few more top plates to set.
  • Mis-located door to family room reframed.

Wednesday, December 27th, 2000

  • The remainder of the second floor wall are done.

Tuesday, December 26th, 2000

Friday, December 22nd, 2000

Monday, December 18th, 2000

Friday, December 15th, 2000

Thursday, December 14th, 2000

  • Second floor deck joists all set and half the floor is decked with plywood.

Friday, December 8th, 2000

Thursday, December 7th, 2000

  • No work today

Wednesday, December 6th, 2000

  • Final prep for the second floor deck. However, the day was cut short due to an accident. One of the more experienced framers fell into the stair hole onto the basement slab. He suffers multiple base-skull fractures and a broken foot. I’ll spare you all the details, but he seems OK now.

Tuesday, December 5th, 2000

Monday, December 4th, 2000

  • The last of the interior walls are up and top plates installed.

Saturday, December 2nd, 2000

Tuesday, November 28th, 2000

Monday, November 27th, 2000

  • First floor deck is complete. Walls start tomorrow.

Tuesday, November 21st, 2000

Tuesday, November 21st, 2000

  • Hammers and nail guns rang out today as framing finally got underway. All but one of the remaining sill plates were laid out and about half of the first floor I-beam joists were placed.

Monday, November 20th, 2000

  • No work started today due to the being opening day of the deer hunting season. Around here, very few native Virginians are at work on this sacred day.

Saturday, November 18th, 2000

  • Closer inspection of the house revealed that Gary Cramer (slab guy) did, in fact, pour the footing for the three porch piers in the front of the house. This will allow the mason to block up these several deep piers so backfilling can be completed. At least most of the wall lumber arrived. However, the engineered floor joists are missing. Hmm…

Thursday, November 16th, 2000

  • Met with Craig and Dale to review the engineering drawings worked up by the joist firm. They were inadvertently given the wrong version of prints so their drawings were all wrong. We discussed the needed corrections and concluded that the first shipment had more than enough to properly frame the first floor deck. That shipment was expected some time Friday so we agreed Dale would start framing Monday the 20th.

Tuesday, November 14th, 2000

  • On the way home from the airport, we stopped by the house to see what got done (or didn’t get done). We were pleased to find that the basement and garage slabs got poured on Wednesday the 8th, but not much otherwise. I had a feeling that the framing didn’t start, and I was right. But it wasn’t the fault of the framer…the lumber hadn’t arrived! But it wasn’t the lumber guy’s (Craig from Tart Lumber) fault, either. There was some confusion on the engineering for the I-beam floor joists that delayed getting the lumber delivered from the factory to Craig, so he couldn’t deliver anything himself. Oh well, it wasn’t like I was expecting much work getting done while I was scuba diving in the Bahamas.

Friday, November 3rd thru Tuesday, 14th, 2000

  • Enjoyed the warmth of Miami and the Bahamas while not much got done on the house.

Friday, November 2nd, 2000

  • Spent some time this morning meeting with Dale Conklin (the framer) to go over the last minute details. The lumber is to be delivered in several days and the slabs would be in soon. And most imminently, I was about to fly south for a long-planned family vacation so I wanted to get as much queued up as possible.

Thursday, November 2nd, 2000

  • I got hold of the plumbing inspector this morning and he told me my pipes looked fine. But he failed me for the water test. I had put some water in the pipes (mostly filled) and left a full bucket next to it for him to use to check for himself. But he said declined to pour the water himself. After swallowing hard and barely containing my rage, I politely thanked him and hung up. Cooled off for a few minutes then called him back. Could he please meet me there this morning for the test? OK. When he arrived, he looked down at my freshly filled pipes and handed be my "PASSED" sticker. But this nonsense cost about three days and now the slab guy had to cancel today’s pour and can’t get back till next Wednesday or Thursday. So now I’ve got to wave-off the framer 4-5 days.

Wednesday, November 1st, 2000

  • Well, I didn’t get my plumbing inspection. The recorded message gives no reason.
  • The slab prep was done today. They laid 4 inches of gravel, a plastic sheet, and wire mesh over the floor of the basement and garage. The garage also was prepped for 2 grade beams running laterally and supported by notches in the slab ledge. Looks very good.
  • The foundation drain pipe was laid, as were the pipes to carry water away from the floor drains and gutters. I faxed in the waterproofing cert and now the waterproofing and draintile inspections passed.

Tuesday, October 31st, 2000

  • Contacted plumbing inspector and found that he didn’t like the configuration of one tee joint. Fine, I’ll redo it, no problem. Also, the line should be filled with water for a water (leak) test. Gregg and I head up to the house at 8:30 and replace the joint by the light of a Coleman lantern. Filled it with water and now we’ll see what else the plumbing inspector doesn’t like.
  • The building inspector reviewed the basement wall’s waterproofing and foundation drain ("draintile"). He gave the excavator the OK to backfill and the excavator filled the garage and backfilled the entire back of the house. (Backfilling the front wall will wait until the deep porch piers are set). However, the Loudoun County Automated Inspection Request Service (AIRS) says the waterproofing inspect fails. I’m told I need to fax in the waterproofing certificate to clear this. And I suspect they’re holding the draintile cert until the final lines are buried. Neither of their items are holding up the project.

Monday, October 30th, 2000

  • My first inspection failure. I was trying to meet the plumbing inspector for a sub-slab rough-in inspection, but he came and went before I got there at lunch time. He rejected it for some reason that was scrawled illegibly on the rejection sticker. Until he can clarify the deficiency, I can’t fix it. The slab work now slips day-for-day until resolved.
  • Met with engineer from the Northern Virginia Electric Cooperative (NOVEC). They will be placing a transformer pole about 250 feet (maximum distance) from the NW corner of the house and from there will drop a line underground and run to our house. We may have power by Christmas. I would have liked to have arranged this earlier, but the house positioning needs to be set before the line run can be established. Good thing the framer has a generator!

Saturday, October 28th, 2000

  • Laid sub-slab plumbing (myself and two friends). Involved digging two "rabbit-holes" underneath the foundation footing. Lesson learned: When the concrete guy is laying out for the footers, ask that a 6" tube be cast below the footing grade so you can slide sewer pipes through without digging. Ran a 4" soil stack and stubbed out for future half bath. Also established 2 floor drains that run "to daylight" meaning they don’t dump in to the septic system.

Friday, October 27th, 2000

  • Installed sills on front walls (only). This was done to provide nailing surface for beam braces.
  • Set all lally columns and 4 of the 6 steel beams. One beam over lower kitchen too short. Will return and replace. Beam over garage door left off until slab work done. No need for it until framing starts on 11/6. The guys knock a thin piece of concrete off when setting the steel and that "tore" off an adjoining 12". The thin piece should not even have been there per the blueprints, and the larger piece can be recast by the mason when he sets the brick veneer on the foundation.

Thursday, October 26th, 2000

  • Delivered the steel basement beams to job site

Wednesday, October 25th, 2000

  • Both plumbing leads dried up, so I’m submitting a "ground work only" plumbing permit application and I’ll do the slab work myself.

Tuesday, October 24th, 2000

Friday, October 20th, 2000

  • The project is moving so fast, but since the framer cannot move his start date any earlier, we’ve rearranged the schedule a bit to make better use of the time. We were going to have the first floor deck installed before backfilling and having slabs poured, but now those will come first. Since the basement slab has a plumbing rough-in, I need to get a plumber here FAST!
  • Removed the forms from the basement walls

Thursday, October 19th, 2000

  • Poured the basement walls

Monday, October 16th, 2000

Saturday, October 14th, 2000

Friday, October 13th, 2000

  • Finished forming footers
  • Footer inspection
  • Poured footers
  • Delivered wall forms

Thursday, October 12th, 2000

  • Garage excavated
  • Minor basement excavation touch-up for front piers by front door
  • Start laying out footer forms

Tuesday, October 10th, 2000

Monday, October 9th, 2000:

  • Re-staked house after slight re-alignment
  • Basement excavation complete
  • Laid gravel on main driveway

Sunday, October 8th, 2000:

Saturday, October 7th, 2000:

Friday, October 6th, 2000:

  • Closing
  • Off-loaded heavy earthmoving equipment (scraper, front end loader)

 

Preliminary Stuff

  • Put offer on land
  • Land under contract
  • Well drilled: 275 feet deep, flows 80 gallon per minute!
  • Well grouted
  • Water sample taken
  • Received good water test results
  • Got building permit approved

We welcome your comments and questions. Please e-mail Piedmont Vintage Homes LLC, please visit the Contact Us page or e-mail the Piedmont Vintage Homes LLC sales department at: sales@piedmontvintagehomes.com
Piedmont Vintage Homes Copyright © 2004