Tuesday, April 10th,
2001
-
Today’s full view:
View 1
-
Window heads
are being made up on site from the same crown molding used under
the eaves.
-
Siding
complete on kitchen and Emily’s
room.
-
Second half of the 2200
board-feet of
poplar
is on its way to the kiln.
Thanks, Gregg!
Sunday, April 8th,
2001
-
By now, all long
rafters
are up, about 30% of ceiling joists and 6 sheets of plywood.
Still to do: rear hip rafter, all jack rafters, remaining
plywood and ceiling joists.
Thursday, April 5th,
2001
-
Rafters start
to go up. All full rafters on north end installed.
Wednesday, April 4th,
2001
-
Last of the
columns
and
beams
are up on the wrap-around porch, as are temporary railings.
Tuesday, April 3rd,
2001
-
The landing and long section of
the
3rd floor stairs
are installed. Perfect fit!
Monday, April 2nd,
2001
-
Three more
columns go up, and all the beams for the erected columns.
-
One thousand
board-feet of sawn poplar is hauled off to the kiln for drying.
This will eventually end up as casing, baseboard, crown molding
and kitchen cabinets.
Sunday, April 1st,
2001
-
Work on the
wrap-around porch begins with the arrival of my father.
Together, we get the first six columns up and one segment of
beam.
Wednesday, March
28th, 2001
-
The roof is finished (almost).
The roofing is multi-tone black Architectural (dimensional)
shingle. The flat roof over the service porch is hand-crimped
standing seam metal. The
roof well
for the guest room window is
copper with soldered joints. All that is left is the shingles
for the four of cornice returns.
Sunday, March 25th,
2001
-
Met with the
plumber and did the layout for the house. We’ll use heavy wall
copper pipe for supply lines and a combination of PVC and cast
iron for the DWV (drain-waste-vent). The cast will only be used
where there are vertical runs from the second floor to keep the
noise suppressed.
Thursday, March 22nd,
2001
Wednesday, March
21st, 2001
-
Upper section
of main staircase re-set. But due to improper sizing by the
manufacturer, this adjustment won’t work. Now the stair treads
are notably tilted!
-
Half wall
along stairs in the sewing room built.
-
Chimney in
sewing room boxed in.
-
Downstairs windows arrived. These are the
old-style windows
with brass chains and sash
weights.
-
The first of
the shop tools delivered. Includes a 12.5 inch thickness planer
and 6x47 inch jointer. These will be needed to make the kitchen
cabinets and raised panels for the foyer and study. A 1.5 HP
shaper is due next week.
Tuesday, March 20th,
2001
Monday, March 19th,
2001
-
Took lots of
stair measurement and plotted the data out with Microsoft Excel.
It helped illustrate just how the upper section of the main
stairs are mis-sized.
Saturday, March 17th,
2001
-
Examined the
main staircase with Dale and discovered that it was installed
improperly. One step didn’t account for the finish floor
thickness on the landing so we’re off by ¾ inches! Dale will
fuss with Monday.
-
Entire second
floor electrical rough-in complete!
-
Installed
small (30A, 2 circuit) sub-panel in woodshop and wired up four
wall outlets for power tools.
Friday, March 16th,
2001
-
Roofing
of main house complete.
-
Well, it’s the
end of the week and the 1st floor windows promised
this week never showed up.
Thursday, March 15th,
2001
-
The roofing
started (rear side) but had to stop due to rain.
-
Entire main
porch deck framing complete.
Tuesday, March 13th,
2001
-
Reviewed
hearth with mason. He made it three inches narrower on each
side. To accomplish this he ripped six inches off the center
piece of slate. Looks all wrong, and he will reset it the full
width.
Monday, March 12th,
2001
-
Last footing
for service porch poured. Ash cleanout door installed. Slate
hearth set. All but 4 steel beam pockets in foundation sealed up
with mortar.
-
Rear section
of porch deck is framed.
Sunday, March 11th,
2001
Saturday, March 10th,
2001
-
Lower section of main stairs removed and
landing
lowered 8". A triangle section was added to bring part of
landing up to original height.
-
Main porch
piers still in work. Some were thought to be done only to
discover they were too short. The mason had the wrong reference
point from which to measure. Four more courses of brick will
work nicely.
-
Table saw and mini-workbench brought into
woodshop.
Friday, March 9th,
2001
Thursday, March 8th,
2001
-
"Winder"
landing solution chosen for main staircase. Stair manufacturer
blessed this idea and will ship us an extra riser and tread
nosing to accomplish this.
-
Eaves completed on
rear bump-out (family room).
Tuesday, March 6th,
2001
-
Basement stairs set successfully.
-
Main staircase installation, but not so successfully. The
lower segment and landing
was installed, but insufficient headroom was provided for by the
stair supplier. He took lots of measurements but simply goofed
somewhere. In his setup, there are 6 steps to the landing and
then 9 more to 2nd floor. But those 6 lower treads
cause the steps to stick out into the foyer a bit too far and
the tread under the edge of the ceiling opening is only 6’-4"
above the steps (should be 6’-8"). One solution is to lower the
landing, remove one tread from the lower segment, and add a
"winder" to the landing. That will keep the upper (expensive)
segment from needing to be rebuilt.
-
Main porch piers
have been started.
Sunday, March 4th,
2001
-
More
electrical wiring. Getting close to completing.
-
Trim work on
garage gable finished.
Wednesday,
February 28th, 2001
-
Service porch
framing completed.
Tuesday, February
27th, 2001
Monday, February
26th, 2001
Saturday, February
24th, 2001
-
Chimney built
up to roof deck.
Friday, February
23rd, 2001
-
Fireplace
boxed-in in the family room.
-
Lower segment
of the laundry chute built.
-
Lighting
established on 2nd and 3rd floor.
Thursday, February
22nd, 2001
Wednesday,
February 21st, 2001
Tuesday, February
20th, 2001
-
Built the two
wide front porch piers.
-
Last of the
materials (fire brick, sand, flue tiles) arrive for the building
of the fireplace tomorrow.
Sunday, February
19th, 2001
-
Finished the
ductwork rough-in.
Saturday, February
18th, 2001
-
Wired up the
lighting in the basement.
-
Installed
ductwork in the wood shop to heat/cool the lower kitchen.
Thursday, February
15th, 2001
Wednesday,
February 14th, 2001
-
Had the
electrical rough-in inspection. Lots of items he wants done but
nothing unexpected.
Tuesday, February
13th, 2001
Monday, February
12th, 2001
-
Third floor
windows set.
-
Roof papered.
Technically, we are now "dried-in".
-
Miscellaneous
framing punchlist items fixed.
Sunday, February
11th, 2001
-
My friend Gregg
and I worked all day to finish (almost) the 3rd and 1st
floor wiring. Some minor items to deal with, and the basement
needs lights, but I’m pressing ahead for an electrical rough-in
inspection on Tuesday.
Saturday, February
10th, 2001
-
Today’s views:
View 1,
View 2
-
Upper heating
ductwork install started.
-
Third floor
wiring started.
Friday, February 9th,
2001
-
POWER! After
months of paperwork and delays, we have power. Gentlemen, do NOT
start your generators.
-
Second floor
windows installed.
Thursday, February
8th, 2001
-
Northern
Virginia Electric Co-operative finally starts work. A power pole
is send way down the front yard with a transformer. A trench for
the buried power line is dug from the pole to the rear of the
house where I installed the meter box. The buried cable was laid
and mostly filled in.
-
Electrical
rough-in of second floor 100% complete.
Wednesday,
February 7th, 2001
-
The second
floor, third floor and garage windows arrive.
-
All components
for the Rumford fireplace arrive.
Monday, February 5th,
2001
-
Six loads of
#3 gravel spread as new base for driveway.
-
Rear gable
framed and ready for paper.
-
Garage
"clipped-gable" framed and ready for paper.
Sunday, February 4th,
2001
-
Lots more
wiring complete this weekend.
Friday, February 2nd,
2001
-
Dormer roofs
framed. Top roof ready for paper.
Thursday, February
1st, 2001
-
Fireplace
materials and 2/3rd of the windows delivered, but
couldn’t get up the driveway due to massive mud ruts in
driveway. The snow-melt and rain have sunk the undersized base
gravel. Need lotsa #3 gravel and FAST!
-
Dormer walls
framed.
-
3rd
floor knee walls framed.
-
Measured for
staircases.
Monday, January 29th,
2001
-
All sheathing
complete on front roof surfaces.
-
Completed
second floor wiring,
except for the bathrooms.
Sunday, January 28th,
2001
-
Roof rafters
complete, sheathing begins. Still need dormers.
-
Pulled most of
the wires for the second floor.
Saturday, January
27th, 2001
-
All (well,
most) stud holes drilled for wiring.
-
Started to
pull wires on the second floor.
Tuesday, January
23rd, 2001
Wednesday, January
17th, 2001
Tuesday, January
16th, 2001
-
Last of gable
trim installed.
-
With the help of a
crane,
the
rear gable
over the family room was lowered into place.
-
Then the
north gable and
south gables were erected.
-
Lastly, the steep
front gable was erected.
-
The
ridge beam
(made up of several 1.75 x 14" microlams nailed together) was
lowered and supported and stabilized with four temporary
rafters.
-
All
trusses
over garage and lower kitchen were set.
Monday, January 15th,
2001
-
Garage walls were erected and trued up today.
-
The second
floor deck was corrected for the laundry chute.
-
Pulled 3 more circuits. Twelve circuits wired up. Just about done
the
breaker box.
Sunday, January 14th,
2001
-
Almost completed the
north gable,
south gable, and
front gable. Only minor trim to complete before raising.
-
Garage walls framed. Will tip up on Monday.
-
All
basement ductwork
in place except for ducts under lower kitchen. This will require
a 9x13 inch hole cut into concrete wall, and the mason says he
can do this Monday. Ductwork for 2nd and 3rd
floor will wait until dry-in.
-
Pulled nine 2nd
and 3rd floor circuits. I’ll wire them up Monday
night.
Saturday, January
13th, 2001
-
Framing of
three main roof gables complete. Interior trim being installed.
-
All foundation brickfacing complete. Looks great! The
corner brick in the second course is a brick from the original Sugar Bowl
stadium. This hold lots of sentimental value, as the Sugar Bowl
was the stadium of my Alma Mater, Tulane University.
-
HVAC guys
arrive to start heating install. All first floor holes cut to
use my antique floor registers.
-
Mason
completed all brick facing of exposed foundation.
Thursday, January
11th, 2001
-
Completed 3rd floor deck. Quite a view from up there
from
West,
South,
East,
and
North.
-
Began to frame
three main roof gables. Will install most exterior trim first,
then use a crane to tip them up in place.
-
Mason faced
the rear of house foundation with brick.
-
Wired up the
main run of 3 more circuits.
-
HVAC folks
deliver ductwork.
Tuesday, January 9th,
2001
-
Wired up the
main run of the first 8 circuits.
Saturday, January
6th, 2001
-
Last of 3rd
floor joists installed and most plywood placed. Ran out of
plywood so will continue Monday.
Wednesday, January
3rd, 2001
-
Hearth
inspection successful. Mason must tweak the re-bar position
slightly to accommodate the basement furnace flue and the ash
door, but otherwise he’s ready to pour the fireplace slab when
we get a warm day.
-
Most 3rd
floor joists set. Need another beam member for stair opening and
then last of joists can be set. Expect this and plywooding on
Friday.
Tuesday, January 2nd,
2001
-
The mason
prepped the top of the chimney foundation for the
fireplace/hearth slab. Inspection called for tomorrow.
Monday, January 1st,
2001
-
I mounted the
main and auxiliary circuit breaker panels on the side of the
chimney foundation. I then tied them into the main service
entrance.
Sunday, December
31st, 2000
Friday, December
29th, 2000
-
Last of top
plate installed.
-
The 3rd
floor deck has started.
-
I’ve installed the
meter box
and the main breaker and gotten it partially wired up.
-
Concrete block and one ton of sand on site in preparation for fireplace/chimney
foundation.
Thursday, December
28th, 2000
-
All interior
and exterior second floor walls are complete. Just a few more
top plates to set.
-
Mis-located
door to family room reframed.
Wednesday,
December 27th, 2000
-
The remainder
of the second floor wall are done.
Tuesday, December
26th, 2000
Friday, December
22nd, 2000
-
Tuesday thru
Thursday was lost due to several inches of snow. The other
exterior walls of the second floor are framed, but need
sheathing
and Tyvek before erecting.
Monday, December
18th, 2000
-
The front and
rear exterior walls are framed and erected.
Friday, December
15th, 2000
-
The second
floor deck is complete and layout of the 2 floor walls has
started.
Thursday, December
14th, 2000
-
Second floor
deck joists all set and half the floor is decked with plywood.
Friday, December 8th,
2000
-
First floor
deck gets it’s X-bracing post-installed and all "squash block"
are set on both side of each floor joint under each load bearing
wall.
-
First of the
second floor joists are set (over dining room and kitchen).
Large laminated beam set over family room to support wall of
guest room above.
Thursday, December
7th, 2000
Wednesday,
December 6th, 2000
-
Final prep for
the second floor deck. However, the day was cut short due to an
accident. One of the more experienced framers fell into the
stair hole onto the basement slab. He suffers multiple
base-skull fractures and a broken foot. I’ll spare you all the
details, but he seems OK now.
Tuesday, December
5th, 2000
-
All the walls
are now braced to ensure that they stay put while the second
floor deck is set.
Monday, December 4th,
2000
-
The last of
the interior walls are up and top plates installed.
Saturday, December
2nd, 2000
-
Framing is
mostly complete on the first floor. All exterior walls are up
(except garage) and most interior walls, too. All that remains
is two walls of the family room and the powder room & pantry.
Work progressing smoothly and I’m impressed with the quality of
the work. The punch list is growing, but only with trivial
items.
Tuesday, November
28th, 2000
-
Walls start
framing (horizontally). They’ll go up this afternoon.
Monday, November
27th, 2000
-
First floor
deck is complete. Walls start tomorrow.
Tuesday, November
21st, 2000
-
Framing
continued on the first floor deck. All joists are set and about
80% of the ¾" tongue & grooved plywood floor decking has been
glued and nailed. Only the lower kitchen area remains to be
covered.
Tuesday, November
21st, 2000
-
Hammers and
nail guns rang out today as framing finally got underway. All
but one of the remaining sill plates were laid out and about
half of the first floor I-beam joists were placed.
Monday, November
20th, 2000
-
No work
started today due to the being opening day of the deer hunting
season. Around here, very few native Virginians are at work on
this sacred day.
Saturday, November
18th, 2000
-
Closer inspection of the house revealed that Gary Cramer (slab guy)
did, in fact, pour the footing for the three porch piers in the
front of the house. This will allow the mason to block up these
several deep piers so backfilling can be completed. At least
most of the
wall lumber arrived. However, the engineered floor joists are missing. Hmm…
Thursday, November
16th, 2000
-
Met with Craig
and Dale to review the engineering drawings worked up by the
joist firm. They were inadvertently given the wrong version of
prints so their drawings were all wrong. We discussed the needed
corrections and concluded that the first shipment had more than
enough to properly frame the first floor deck. That shipment was
expected some time Friday so we agreed Dale would start framing
Monday the 20th.
Tuesday, November
14th, 2000
-
On the way home from the airport, we stopped by the house to see
what got done (or didn’t get done). We were pleased to find that
the
basement
and
garage
slabs got poured on Wednesday the 8th, but not much
otherwise. I had a feeling that the framing didn’t start, and I
was right. But it wasn’t the fault of the framer…the lumber
hadn’t arrived! But it wasn’t the lumber guy’s (Craig from Tart
Lumber) fault, either. There was some confusion on the
engineering for the I-beam floor joists that delayed getting the
lumber delivered from the factory to Craig, so he couldn’t
deliver anything himself. Oh well, it wasn’t like I was
expecting much work getting done while I was scuba diving in
the Bahamas.
Friday, November 3rd
thru Tuesday, 14th, 2000
-
Enjoyed the
warmth of Miami and the Bahamas while not much got done on the
house.
Friday, November 2nd,
2000
-
Spent some
time this morning meeting with Dale Conklin (the framer) to go
over the last minute details. The lumber is to be delivered in
several days and the slabs would be in soon. And most
imminently, I was about to fly south for a long-planned family
vacation so I wanted to get as much queued up as possible.
Thursday, November
2nd, 2000
-
I got hold of
the plumbing inspector this morning and he told me my pipes
looked fine. But he failed me for the water test. I had put some
water in the pipes (mostly filled) and left a full bucket next
to it for him to use to check for himself. But he said declined
to pour the water himself. After swallowing hard and barely
containing my rage, I politely thanked him and hung up. Cooled
off for a few minutes then called him back. Could he please meet
me there this morning for the test? OK. When he arrived, he
looked down at my freshly filled pipes and handed be my "PASSED"
sticker. But this nonsense cost about three days and now the
slab guy had to cancel today’s pour and can’t get back till next
Wednesday or Thursday. So now I’ve got to wave-off the framer
4-5 days.
Wednesday,
November 1st, 2000
-
Well, I didn’t
get my plumbing inspection. The recorded message gives no
reason.
-
The slab prep was done today. They laid 4 inches of gravel, a
plastic sheet, and wire mesh over the floor of the
basement
and
garage.
The garage also was prepped for 2 grade beams running laterally
and supported by notches in the slab ledge. Looks very good.
-
The
foundation drain pipe
was laid, as were the pipes to carry water away from the floor
drains and gutters. I faxed in the waterproofing cert and now
the waterproofing and draintile inspections passed.
Tuesday, October
31st, 2000
-
Contacted
plumbing inspector and found that he didn’t like the
configuration of one tee joint. Fine, I’ll redo it, no problem.
Also, the line should be filled with water for a water (leak)
test. Gregg and I head up to the house at 8:30 and replace the
joint by the light of a Coleman lantern. Filled it with water
and now we’ll see what else the plumbing inspector doesn’t like.
-
The building
inspector reviewed the basement wall’s waterproofing and
foundation drain ("draintile"). He gave the excavator the OK to
backfill and the excavator filled the garage and backfilled the
entire back of the house. (Backfilling the front wall will wait
until the deep porch piers are set). However, the Loudoun County
Automated Inspection Request Service (AIRS) says the
waterproofing inspect fails. I’m told I need to fax in the
waterproofing certificate to clear this. And I suspect they’re
holding the draintile cert until the final lines are buried.
Neither of their items are holding up the project.
Monday, October 30th,
2000
-
My first
inspection failure. I was trying to meet the plumbing inspector
for a sub-slab rough-in inspection, but he came and went before
I got there at lunch time. He rejected it for some reason that
was scrawled illegibly on the rejection sticker. Until he can
clarify the deficiency, I can’t fix it. The slab work now slips
day-for-day until resolved.
-
Met with
engineer from the Northern Virginia Electric Cooperative
(NOVEC). They will be placing a transformer pole about 250 feet
(maximum distance) from the NW corner of the house and from there
will drop a line underground and run to our house. We may have
power by Christmas. I would have liked to have arranged this
earlier, but the house positioning needs to be set before the
line run can be established. Good thing the framer has a
generator!
Saturday, October
28th, 2000
-
Laid sub-slab
plumbing (myself and two friends). Involved digging two
"rabbit-holes" underneath the foundation footing. Lesson
learned: When the concrete guy is laying out for the footers,
ask that a 6" tube be cast below the footing grade so you can
slide sewer pipes through without digging. Ran a 4" soil
stack and stubbed out for future half bath. Also established 2
floor drains that run "to daylight" meaning they don’t dump in
to the septic system.
Friday, October 27th,
2000
-
Installed
sills on front walls (only). This was done to provide nailing
surface for beam braces.
-
Set all lally columns and 4 of the 6
steel beams. One beam over lower kitchen too short. Will return and replace.
Beam over garage door left off until slab work done. No need for
it until framing starts on 11/6. The guys knock a thin piece of
concrete off when setting the steel and that "tore" off an
adjoining 12". The thin piece should not even have been there
per the blueprints, and the larger piece can be recast by the
mason when he sets the brick veneer on the foundation.
Thursday, October
26th, 2000
-
Delivered the
steel basement beams to job site
Wednesday, October
25th, 2000
-
Both plumbing
leads dried up, so I’m submitting a "ground work only" plumbing
permit application and I’ll do the slab work myself.
Tuesday, October
24th, 2000
Friday, October 20th,
2000
-
The project is
moving so fast, but since the framer cannot move his start date
any earlier, we’ve rearranged the schedule a bit to make better
use of the time. We were going to have the first floor deck
installed before backfilling and having slabs poured, but now
those will come first. Since the basement slab has a plumbing
rough-in, I need to get a plumber here FAST!
-
Removed the forms from the
basement walls
Thursday, October
19th, 2000
-
Poured the
basement walls
Monday, October 16th,
2000
Saturday, October
14th, 2000
Friday, October 13th,
2000
-
Finished
forming footers
-
Footer
inspection
-
Poured footers
-
Delivered wall
forms
Thursday, October
12th, 2000
-
Garage
excavated
-
Minor basement
excavation touch-up for front piers by front door
-
Start laying
out footer forms
Tuesday, October
10th, 2000
Monday, October
9th, 2000:
-
Re-staked
house after slight re-alignment
-
Basement
excavation
complete
-
Laid gravel on
main driveway
Sunday, October
8th, 2000:
-
A bit more
house site clearing
-
Cleared area
for drain field
-
Staked out
house for excavator
Saturday, October
7th, 2000:
Friday, October
6th, 2000:
-
Closing
-
Off-loaded
heavy earthmoving equipment (scraper, front end loader)
Preliminary Stuff
-
Put offer on
land
-
Land under
contract
-
Well
drilled: 275 feet deep, flows 80 gallon per minute!
-
Well grouted
-
Water sample
taken
-
Received good
water test results
-
Got building
permit approved
|
|